Row colors in the Shared Components table
The Shared Components section on a Production Run detail page uses row background colors to show material procurement status at a glance. A legend at the top-left of the section shows a swatch for each color.
Row appearance | What it means |
|---|---|
White / no highlight | No shortage and no purchase order linked yet. The material is covered by on-hand stock or has no procurement action yet. |
Light blue background | A purchase order is already linked to this row (status is PO Pending or PO Received). No further buying action is needed for this material. |
Light red background | The material has a shortage — required quantity exceeds what is available (on-hand minus committed, plus any allocated incoming). |
Light red background + blue left border | The row has both a shortage and a linked purchase order. The PO exists but may not fully cover the gap, or stock has not yet been received. |
PO Status column
The PO Status column in the same table shows a text label for each row:
No PO — no purchase order is linked to this material line yet.
PO Pending — a PO is linked and the material is on order but not yet fully received.
PO Received — the linked PO has been fully received.
Typical workflow
Open Inventory → Work Orders → Production Runs and select your run.
Scroll to the Shared Components section.
Check red rows — these materials have a shortage.
If the red row also has a blue left border, a PO already exists. Verify the PO quantity covers the shortage, or receive the stock if it has arrived.
If the red row has no blue border and shows No PO, use Generate Purchase Orders or Allocate from Incoming (in the row's ⋮ menu) to address the gap.
Blue rows with no red background can be ignored — procurement is already underway.