Why are materials highlighted in red?

Last updated: September 30, 2026

Red highlights on Shared Components or BOM rows mean a raw material shortage — here's how Luminous calculates it and how to fix it.

Collection: Work Orders: FAQ & Troubleshooting
Priority: P0


Short answer

A material row is red when Luminous calculates a shortage — you do not have enough on-hand or allocated incoming stock to cover the work order's requirement.

How shortage is calculated

Shortage = Required − Available − Inc. Allocated

  • Required — Total qty needed for work order(s) in the run

  • Available — On Hand minus Committed (All): stock not already reserved by other work orders (can be negative)

  • Inc. Allocated — Qty reserved from open POs via Allocate from Incoming

If the result is greater than zero, the row shows a shortage (highlighted red).

Common causes

Cause

Fix

No stock on hand

Generate purchase orders

Stock on order but not allocated

Allocate from Incoming

PO received but not linked

Bulk Receive from work order sidebar

Demand from other active work orders

Check Committed (All) column — other WOs may hold stock

After receiving POs

Once you bulk-receive linked POs, shortages should clear and red highlighting disappears. Only then should you move the work order to In Progress.