How do I edit a line item's ordered quantity or unit cost without opening the purchase order?
Last updated: October 11, 2026
Editing ordered quantity and unit cost in the Line Items view
You can correct a line's ordered quantity and unit cost directly in the cross-PO Line Items grid without navigating into the parent purchase order.
Permissions required
Field | Permission needed |
|---|---|
Ordered (quantity) | Standard purchase order access |
Unit Cost | The |
How to edit
Go to Inventory → Purchase Orders and open the Line Items tab.
Locate the line you want to update.
Double-click the Ordered or Unit Cost cell.
A number editor appears in the cell.
Type the new value and press Enter (or click away) to save.
The cell saves immediately. A confirmation appears at the bottom of the screen.
If the save fails, the cell reverts to the previous value and an error message explains why.
Validation
Ordered quantity must be greater than zero. Entering zero or a negative number is rejected before it reaches the server.
Unit Cost must be zero or greater. Negative values are rejected. A cost of zero is valid (free line).
What updates when you save
Because ordered quantity feeds derived figures, the server returns the full updated row after a quantity save. The following columns refresh in place without a page reload:
Ordered
Remaining to ship
Remaining to receive
Line Total (if cost columns are visible)
Line Status
Saving a unit cost update refreshes the Unit Cost and Line Total cells.
Limitation
In-cell editing is not available on the single-PO detail view — use the PO's own edit form there. The cross-PO Line Items tab is the only surface that offers this shortcut.