Short answer

  • A Work Order is one manufacturing job: a single finished SKU + planned quantity + BOM.

  • A Production Run is a container that groups multiple related work orders processed together as a batch.

Work Order

Each work order tracks:

  • One finished good SKU

  • Planned quantity to produce

  • Bill of materials (components required)

  • Its own status (Draft → Planned → In Progress → Completed)

  • Expected completion date (can differ per work order in a run)

  • Linked purchase orders, assembly orders, and transfer orders

Create individually from Inventory → Work Orders → Orders → Create Work Order.

Production Run

A production run provides:

  • A shared co-manufacturer, production location, and destination warehouse

  • A Shared Components view that consolidates material demand across all work orders in the run

  • Bulk actions: Generate Purchase Orders, Quick Complete, status changes

  • Run-level expected completion date and progress metrics

Create from Inventory → Work Orders → Production Runs → Create Run.

How they relate

  • Creating a production run with multiple SKUs creates one work order per SKU under that run.

  • You can also create standalone work orders and link them to a run later.

  • Bulk-creating 2+ work orders at once auto-creates a production run.

Which should I use?

Scenario

Use

One SKU, one-off job

Single Work Order

Multiple SKUs, same co-man batch

Production Run

Shared raw material purchasing across SKUs